Vopak delays investment on South African LNG project to 2028

  • Vopak, Transnet in consortium to build, run project for 25 yrs
  • Deal talks with Eskom, ExxonMobil; Zululand terminal aims for 2 MMtpy–5 MMtpy LNG import

Dutch tank storage and terminal operator Vopak has pushed back a final investment decision (FID) on South Africa's first liquefied natural gas terminal to 2028, a senior executive said on Wednesday.

The company had planned to approve the project earlier this year, but a September court order halted power utility Eskom's plans to develop a 3,000-megawatt (MW) gas-powered plant at Richards Bay, slowing progress.

"We were waiting to see what was happening with Eskom and we just extended our pre-FEED study," Oliver Naidu, president of Vopak's local unit, said on the sidelines of an energy conference, referring to an early design study.

The company now expects to be ready to make the final decision in the first quarter of 2028, he said. The two-phase project is estimated to cost around $1 B.

Vopak in consortium picked to build, run the project. Vopak was selected in 2024 as part of a consortium with Transnet Pipelines to build and run the Zululand Energy terminal at Richards Bay port for 25 yrs.

Naidu said they expected to sign preliminary agreements with Eskom, and potentially U.S oil major ExxonMobil, in the coming months for LNG use and distribution. Exxon is one of the strong potential customers, he said.

ExxonMobil, a global LNG supplier, previously identified South Africa as a top priority market. The company did not immediately respond to a request for comment.

The Zululand Energy terminal, situated along South Africa's east coast, was expected to initially import 2 MMtpy of LNG by 2027 before ramping up to 5 MMtpy, the Transnet National Ports Authority (TNPA) has said previously.