Chevron plans maintenance at Gorgon LNG export plant in Australia
Chevron Corp is planning to conduct maintenance rounds at its Gorgon liquefied natural gas (LNG) project through two separate periods this year and in 2020, according to a notice on the energy company's website.
![]() |
| Source: EWA |
The company planned to shut more than half an LNG train at the facility from Oct. 11 to Nov. 29, and more than 1 LNG train over May 23-July 11, next year, according to the notice.
A company spokesman could not immediately be reached for comment.
The three-train Gorgon project, one of the world's largest natural gas projects, can produce 15.6 million tons of LNG annually from its three trains, according to Chevron's website.
Chevron is the Gorgon project operator, with its Australian subsidiary holding a controlling 47.3%. Exxon Mobil Corp and Royal Dutch Shell each have a 25% share, and the remainder is held by Japan's Osaka Gas, Tokyo Gas and JERA.
Expected dates Scope of train shutdown
11/10/2019 - 29/11/2019 Shutdown of more than one-half of a train,
but not greater than one LNG train
23/05/2020 - 11/07/2020 Shutdown of more than one LNG
Train, but not bigger than one-and-a-half LNG trains
- Freeport LNG export plant in Texas to take in more natgas after unit shut on Monday
- LNG cool-down vessel arrives at ExxonMobil's Golden Pass plant in Texas
- Freeport LNG export plant in Texas reports shutdown of liquefaction train
- TotalEnergies and Mozambique announce the full restart of the $20-B Mozambique LNG project
- Five energy market trends to track in 2026, the year of the glut


Comments