Substantial Completion of Train 5 at the Sabine Pass Liquefaction Project
HOUSTON--(BUSINESS WIRE)--Cheniere Energy Partners, L.P. announced that Substantial Completion of Train 5 of the Sabine Pass liquefaction project in Cameron Parish, Louisiana (the "SPL Project") was achieved on March 7, 2019. Commissioning has been completed and Cheniere Partners’ EPC partner Bechtel Oil, Gas and Chemicals, Inc. (“Bechtel”) has turned over care, custody, and control of Train 5 to Cheniere Partners.
Under sale and purchase agreements ("SPAs") with Centrica plc and Total Gas & Power North America, Inc., the date of first commercial delivery is expected to occur in September 2019, upon which the term of each of these SPAs commences.
Cheniere Partners and Bechtel have now declared Substantial Completion on five liquefaction trains at the SPL Project ahead of each train’s guaranteed completion date and within project budgets. With the achievement of Substantial Completion, financial results of LNG sales from Train 5 going forward will be reflected in the statement of operations of Cheniere Partners and its applicable affiliates.
- Freeport LNG export plant in Texas reports shutdown of liquefaction train
- TotalEnergies and Mozambique announce the full restart of the $20-B Mozambique LNG project
- Five energy market trends to track in 2026, the year of the glut
- RWE strengthens partnerships with ADNOC and Masdar to enhance energy security in Germany and Europe
- Venture Global wins LNG arbitration case brought by Spain's Repsol

Comments