Japan's Inpex sees minimal cost overrun on Ichthys LNG project
5/12/2017
TOKYO (Reuters) -- Japan's biggest oil and gas explorer Inpex Corp sees minimal cost overruns on its Ichthys LNG export plant in Australia because of a start-up delay, a senior executive said on Friday.
The cost overrun could be up to a few percent if any, and there would be no material impact to the project, Inpex's Senior Managing Executive Officer Masahiro Murayama told Reuters on the sidelines of the company's full-year earnings results.
Inpex two weeks ago delayed the Ichthys start by up to six months from its original target of the third quarter this year, citing delays in the installation of offshore production facilities.
Reporting by Osamu Tsukimori; Editing by Christian Schmollinger
Sign up to Receive Our Newsletter
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- Qatar’s Ras Laffan LNG hub hit by missile attack, ‘extensive damage’ reported
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- Iran attacks wipe out 17% of Qatar’s LNG capacity for up to five years
- Kazakhstan decides against Shell, Eni participation in Karachaganak gas plant project

Comments