Siemens secures order for largest LNG-to-power complex in Latin America

Siemens Energy has secured an order for the turnkey construction of the combined cycle power plant UTE GNA II in the integrated LNG-to-Power project GNA II, located at Port of Açu, in the Brazilian state of Rio de Janeiro. Construction of the power plant is already ongoing for the project company Gás Natural Açu (GNA). 

Following the successful commissioning of GNA I in summer 2021, GNA II will be the second turnkey combined cycle power plant that Siemens Energy will build in the thermoelectric hub and will add further capacity of 1.7 gigawatts (GW). With a combined capacity of 3 GW the two power plants will be able to provide enough electricity for the consumption of around 14 MM households. The second order comes with the first application of the highly efficient HL class gas turbine in Brazil. The combined cycle plants powered by LNG will be the most efficient thermal power plants in Latin America. Total project amount is approximately €1 B. 

The scope for Siemens Energy foresees the entire power island delivery, that consists in three HL class gas turbines, one steam turbine, four electric generators and three heat recovery steam generators, in addition to instrumentation and control systems. The services offered by Siemens Energy will also cover long-term operation and maintenance of the plant, including advanced remote monitoring and diagnostics by the Remote Operation Center, located in Jundiaí, São Paulo. The power plant is being built together with the consortium partner Andrade Gutierrez who will provide the civil works, the infrastructure and the erection works.  

“Our participation in this outstanding project reinforces how our comprehensive LNG-to-Power approach increases value to our partners, and also meets the need for affordable and reliable energy,” said Jochen Eickholt, Executive Board Member of Siemens Energy AG. “This project is strategic, not only for its grandeur, but also for its geographical location, close to the two main gas pipelines systems in Brazil, in the Northeast and Southeast of the country. And not to forget: Our gas turbines for GNA II are ready to burn hydrogen in the future. This means our technology is future-proof for our customers,” Eickholt added. 

The Açu natural gas project includes the construction of two thermal power plants, as well as an LNG regasification terminal, based on a floating storage regasification unit, plus substations and transmission lines to connect the plants to the National Interconnected System. The thermoelectric complex is part of the Açu Gás Hub, a project under development at the Açu Port Complex aimed to provide a logistical solution for the receipt, processing, conversion to electricity and transport of natural gas in the Campos and Santos basins, as well as for importing and storing LNG. A second phase will comprise additional thermal power projects under the environmental license for 6.4 GW owned by GNA. 

The construction of the GNA I plant started in January 2018 and this plant began its commercial operation in September 2021. The two power plants will supply energy to regions such as Espírito Santo, Minas Gerais and Rio de Janeiro within the National Interconnected System. 


Copyright © 2019. All market data is provided by Barchart Solutions. Futures: at least a 10 minute delay. Information is provided 'as is' and solely for informational purposes, not for trading purposes or advice. To see all exchange delays and terms of use, please see disclaimer.

                                  CMEGroup                                     Icelogo

FEATURED COLUMNS

Editorial Comment
-Adrienne Blume
The editors of <i>Hydrocarbon Processing</i>, sister publication to Gas Processing & LNG, will release their “HPI Market Data 2022” annual forecast report in October.
Industry Focus: Sensor advances allow pipeline leak detection to take to the skies
-Doug Baer
Sustainability and green initiatives have always been laudable objectives, with mission statements around the world confirming commitments to lower emissions and energy consumption, and increase recyclability, to name a few.
Maintenance and Reliability: Prevent unplanned shutdowns for LNG liquefaction facilities
-Peter Zhang
Although an unplanned shutdown is an integrated part of the operational and safety management system of an operating plant, unplanned shutdowns for a modern LNG liquefaction operating facility often become some of the costliest events for the facility owner.
Regional Focus: Balancing Africa’s world-class LNG projects and the environment
-Shem Oirere
The construction of world-scale natural gas processing plants by three of Africa’s top natural gas producers has attracted scrutiny, despite efforts to commercialize the continent’s hydrocarbon resources and expand energy supply on the continent.


Throughput optimization for pipelines and gas plants

Register Now

Many processes within oil and gas pipelines and processing plants depend on maintaining specific temperatures and pressures at which the process fluids are liquids or gases. In addition, anytime water is a component in the process fluid hydrates can form and plug piping and vessels. Learn how Sensia’s Throughput optimization solution allows operators, and control systems to “see inside” the process in real time to understand where the facility is operating with respect to critical physical constants, including the phase envelope and hydrate temperature. This insight allows for more stable operation, reduced energy expenditure and associated emissions, and greater facility throughput. Case studies will include controlling methanol injection, managing heaters, virtual sensors for sulfur recovery units and more.

April 1, 2021 10:00 AM CDT

Register Now

 

Please read our Term and Conditions, Cookies Policy, and Privacy Policy before using the site. All material subject to strictly enforced copyright laws.
© 2021 Gulf Publishing Holdings LLC.